Skip to main content
Search Interpretations

Interpretation ID: nht94-2.91

TYPE: INTERPRETATION-NHTSA

DATE: May 16, 1994

FROM: Gianfranco Venturelli -- Director General, Automobile Lamborghini

TO: Christopher A Hart -- Deputy Administrator, NHTSA

TITLE: FMVSS No. 214, Side Impact Standard Petition

ATTACHMT: Attached to letter dated 8/5/94 from John Womack to John E. Gillick (Std. 214 and Part 555)

TEXT: Dear Mr. Hart:

Automobili Lamborghini S.p.A. (Lamborghini) hereby petitions the National Highway Traffic Safety Administration (NHTSA) to permit Chrysler Corporation (Chrysler) to include Lamborghini vehicles in its vehicle fleet for the purpose of compliance with t he side impact standard's phase-in calculation. n1 In the alternative, Lamborghini petitions NHTSA to grant the company a temporary exemption from the side impact standard requirements until September 1, 1996, pursuant to its authority under 49 C.F.R. @ 555.

n1 Automobili Lamborghini S.p.A., 40019 Sant'Agata Bolognese (BO)-via Modena, 12-Italy, is a joint stock company organized under the laws of Italy. Chrysler Corporation, on January 31, 1994, sold Lamborghini to a group of investors led by MegaTech Lt d., a Bermuda corporation.

Background

On October 30, 1990, NHTSA promulgated revisions to Federal Motor Vehicle Safety Standard No. 214 regarding side

2

impact protection. See 55 Fed. Reg. 45,722 (Oct. 30, 1990) (codified at 49 C.F.R. @ 571.214). Standard 214 specified vehicle crashworthiness requirements in terms of accelerations measured on anthropomorphic dummies in test crashes and specified streng th requirements for side doors. 49 C.F.R. @ 571.214(b). The standard included the following phase-in schedule: (1) at least 10% of a manufacturer's passenger cars produced on or after September 1, 1993, and before September 1, 1994, must comply; (2) at least 25% of passenger cars manufactured on or after September 1, 1994, and before September 1, 1995, must comply; and (3) at least 40% of passenger cars manufactured on or after September 1, 1995, and before September 1, 1996, must comply. 49 C.F.R. @ 571.214 S8. In promulgating the rule, NHTSA recognized that it could take single-line manufacturers up to three years to develop and implement the engineering changes necessary to comply with the standard. 55 Fed. Reg. at 45,749. Accordingly, Standard 214 provides an alternative to the phase-in option. The standard permits manufacturers to delay implementation of the side impact protection standard for one year (until September 1, 1994) if after that date all vehicles produced meet the standard's re quirements. 49 C.F.R. @ 5711.214 S1(d).

As noted supra, Lamborghini was sold by Chrysler on January 31, 1994. Chrysler, as the corporate parent of Lamborghini, had included Lamborghini vehicles in its vehicle fleet for side impact protection compliance purposes. Due to the number of differe nt Chrysler models that required modifications to meet Standard 214, Chrysler elected to comply through the phase-in alternative. Lamborghini vehicles were scheduled to be modified during the last year of the phase-in period because

3

of the relatively low number of vehicles the subsidiary produced and the lead time necessary for engineering and tooling modifications.

Discussion

Chrysler's sale of Lamborghini has placed Lamborghini in a difficult position regarding compliance with the side impact safety standard. Prior to the sale, Lamborghini had a good faith basis for believing that it would not need to meet the requiremen ts of Standard 214 until the production year beginning September 1, 1996 due to its status as part of Chrysler's vehicle fleet. Now that Lamborghini is not part of the Chrysler fleet, the company cannot utilize this flexibility. While the first segment of the phase-in requirement (10% compliance for all passenger cars produced on or after September 1, 1993) has already passed, Lamborghini still could elect Standard 214's alternative compliance date that requires full compliance by September 1, 1994. However, Lamborghini does not now have sufficient lead time to complete the engineering analysis and implement the tooling changes to comply with the standard for the production year beginning either September 1, 1994 or September 1, 1995. In addition, since Lamborghini only produces one model, it cannot phase in compliance even if this were technically possible and the first year of the phase-in period had not already begun. Accordingly, Lamborghini respectfully requests NHTSA to grant this petition to enable Chrysler to count Lamborghini vehicles in Chrysler's fleet for purposes of side impact compliance, or in the alternative, grant Lamborghini a temporary exemption from the requirements of Standard 214. Granting either request would be in the

4

public interest as it will not affect overall motor vehicle safety because Chrysler has agreed to include Lamborghini vehicles in its vehicle fleet for purposes of Standard 214 compliance, thereby ensuring that, consistent with the objectives of the Nati onal Traffic and Motor Vehicle Safety Act, the total number of vehicles meeting the side impact requirements will be the same as if Chrysler had not sold its Lamborghini subsidiary.

I. FLEET AVERAGE CALCULATION.

As part of the contract with MegaTech, Ltd. for the sale of Lamborghini, Chrysler has agreed to include Lamborghini vehicles in its vehicle fleet for purposes of Standard 214 compliance. This action will ensure that the overall number of vehicles com plying with the standard through the phase-in period will be the same as if Chrysler had not sold its subsidiary. This approach gives Lamborghini, a single line manufacturer, the three-year lead time needed to develop and implement the engineering chang es necessary to satisfy the standard's requirement envisioned in the preamble to the final rule. All Lamborghini vehicles produced after September 1, 1996, will satisfy Standard 214.

II. TEMPORARY EXEMPTION.

In the alternative, Lamborghini requests NHTSA to grant the company a temporary exemption to Standard 214 through August 31, 1996, pursuant to 49 C.F.R. @ 555.6(a). In the meantime, as noted above, Chrysler will include, for purposes of production vo lume compliance, all Lamborghini vehicles in Chrysler's phase-in calculations. Beginning September 1, 1996, all Lamborghini vehicles produced will fully comply with the standard.

5

The application of Standard 214 to Lamborghini without adequate leadtime would subject the company to substantial economic hardship. In order to comply with this standard, Lamborghini must modify the door structure and redesign the aperture and door for its automobiles. In view of the extremely short lead time between now and the beginning of production for next year's model, it is simply not possible to complete the necessary engineering and related retooling necessary to meet the September 1, 199 4, target date in the regulations.

Lamborghini is confident, however, that it will be able to comply with the standard by September 1, 1996, but not sooner, in accordance with the following schedule:

1. May 1994 - 1995

- engineering, drawing and development of preliminary prototypes.

2. June 1995 - May 1996

- final tune-up tests, and modification of production tooling.

3. July 1996

- begin production of automobiles in compliance with new Standard 214.

4. September 1996

- delivery of automobiles in compliance with new Standard 214.

The estimated cost of the research and development and the tooling changes necessary to meet the new standards is estimated to be between

6

We would reiterate that the financial hardship this action would cause is primarily due to the absence of sufficient leadtime to implement this standard. Lamborghini had only recently begun analysis of the engineering changes necessary to meet the sta ndard and has not yet begun to implement the necessary tooling changes and purchasing because, until the sale occurred, Lamborghini had a good faith basis for believing it would not have to meet the standard until September 1, 1996.

* * *

Thank you for your consideration in this matter. Please contact Michael J. Grossman, our designated agent for U.S. certification and regulatory liaison (516-829-8694) or John Gillick of Winthrop, Stimson, Putnam & Roberts, our legal counsel (202-775- 9870), if you have any questions about this petition.

Enclosures